Tanjung Intan

Peta Pelabuhan

Dermaga Panjang (m) Lebar (m) Kedalaman
(M LWS)
A Dermaga I 157 15 -11
B Dermaga II 134 25.5 -11
C Dermaga III 50 15 -11
D Dermaga Multipurpose 150 27 -11.5
E Dermaga IV 72 17.4 -10
F Dermaga VI 120 50 -11
G Dermaga Batu Bara 70 16 -7.5

Standar Kinerja Bongkar Muat Peti Kemas

Lokasi Dermaga UPTK Box/CC/Jam Pelabuhan Konvensional Box/Crane/Jam Menerima Menit Pengiriman Menit

Standar Kinerja Bongkar Muat Non Peti Kemas

Lokasi GC (T/G/J) BC (T/G/J) STANDAR UN (T/G/J) CC (T/J) CK (T/J)

Fasilitas dan Peralatan

Fasilitas Bangunan

  • Lapangan Penumpukan 8,7 Ha
  • Gudang 7.100 M²

Fasilitas Peralatan

  • 1 Unit Ship to Shore Crane Kapasitas 35 Ton
  • 2 Unit Forklift Kapasitas 5 Ton
  • 1 Unit Forklift Kapasitas 10 Ton
  • 7 Unit Bucket Kapasitas 15 Ton
  • 2 Unit Rampdoor Ukuran 14 M
  • 1 Unit Rampdoor Ukuran 12 M
  • 4 Unit Grabe Kapasitas 8 Ton
  • 4 Unit Grabe Kapasitas 10 Ton
  • 4 Unit Hopper Kapasitas 8 Ton
  • 4 Unit Hopper Kapasitas 15 Ton

Alur Pelayaran

  • Panjang Alur : 9,5 Mil Laut
  • Lebar Alur : 250 M
  • Kedalaman Alur : -6 s/d -12 MLWS

Sistem Manajemen

  • Manajemen Mutu ISO 9001
  • Manajemen Lingkungan ISO 140001
  • SMK 3 (Bendera Emas)
  • ISPS Code